Habib Construction Services Completed Projects
List View
Serial # | Project Name | Project Cost (Million Rupees) | Client | Ownership | Consultants | Commencement Date | Completion Date |
---|---|---|---|---|---|---|---|
1 | Lahore Ring Road (Package-4) Saggian Interchange | 959 | NLC | PMU Government of Punjab | NESPAK | February 03, 2009 | May 01, 2009 |
2 | Lahore Ring Road Project (Package 13) Construction of Road Portion from Mahmood Booti to Laku Dair | 450 | NLC | PMU Government of Punjab | NESPAK | May 30, 2009 | Oct 30, 2009 |
3 | Lahore Ring Road, (Package-10) Quaid-E-Azam Interchange at GT Road | 1500 | NLC | PMU Government of Punjab | NESPAK | February 25, 2009 | December 31, 2009 (Early Completion) |
4 | Lahore Ring Road, (Package-9) Harbanspura Interchange at Canal Crossing | 1200 | NLC | PMU Government of Punjab | NESPAK | March 01 , 2009 | January 30, 2010 (Early Completetion) |
5 | Lahore Ring Road, (Package-7) Abdullah Gul Interchange Near Lahore Airport | 1015 | NLC | PMU Government of Punjab | NESPAK | September 12, 2009 | June 11 , 2010 (Early Completion) |
6 | Dualization of Lahore Ferozepur Road (Lahore to Kasur) Khaira Distributory to Kahna | 220 | C&W | C&W Government of Punjab | NESPAK | June 25, 2010 | September 24, 2010 |
7 | Dualization of Lahore- Kasur Road Group-3 (Kasur City Portion) | 755 | C&W | C&W Government of Punjab | NESPAK | April 02 , 2010 | October 01 , 2010 |
8 | Improvement of Canal Road Lahore from Thokar Niaz Baig To Defence Road | 315 | C&W | C&W Government of Punjab | ACE (Pvt )Ltd | December 01, 2010 | February 28 , 2011 |
9 | Lahore Ring Road (Package 3-B) Underpass At Jhugian Jodha | 175 | NLC | PMU Government of Punjab | NESPAK | April 15, 2010 | February 28, 2011 |
10 | Lahore Ring Road,(Package-11 and 11-A) Interchange At Ghazi Road and Road Connection Up To Bhata Chowk | 1100 | NLC | PMU Government of Punjab | NESPAK | February 15, 2010 | July 30, 2011 |
11 | Kalma Flyover Lahore | 860 | NLC | C&W Government of Punjab | NESPAK | April 02, 2011 | August 14, 2011 (Completed in record time of 135 days) |
12 | Sohawa , Chakwal , Talagang Mianwali roadSection balkassar Interchange to Terhada | 305 | C&W | C&W Government of Punjab | UMAR MUNSHI | December 11, 2010 | September 30, 2011 |
13 | Improvement/Rehabilitation of Multan Road From Thokar Niaz Baig to Scheme Morr | 575 | NLC | PMU Government of Punjab | NESPAK | August 06, 2009 | Oct 30, 2011 |
14 | Construction of Sialkot International Airport Extension of Apron | 180 | SIAL | SIAL | NESPAK | October 02, 2010 | November 30, 2011 |
15 | Widening / Improvement of Canal Bank Road, from Mall Road to Doctors Hospital Underpass (3.5km) | 166 | NLC | C&W Government of Punjab | NESPAK | October 28, 2011 | January 15, 2012 |
16 | Construction of Flyover at Chandni Chowk, Rawalpindi | 828 | NLC | C&W Government of Punjab | ENGINEERING ASSOCIATES KARACHI | November 05, 2011 | March 10, 2012 (Completed in a record time of 126 days) |
17 | Construction of Flyover at Ferozepur Road Junction (Muslim Town Flyover Lahore) | 2082 | NLC | C&W Government of Punjab | NESPAK | October 28, 2011 | April 21, 2012 (Completed in a record time of 177 days) |
18 | Widening & Improvement of Churr Chowk, GT Road, Rawalpindi | 306 | NLC | C&W Government of Punjab | ECSP | August 09, 2012 | December 01, 2012 |
19 | Construction of Flyover at 6th Road Junction along Murree Road Rawalpindi | 814 | NLC | C&W Government of Punjab | EA CONSULTING (PVT) LTD | September 25 , 2012 | January 03, 2013 (Completed in exactly 100 days and made another record) |
20 | Metrobus Transit System for Lahore Ferozepur Corridor MAO College to Bhatti Chowk (Length 2.5 Km) Package-4 | 2003 | NLC | LDA Government of Punjab | NESPAK | May 29, 2012 | February 10, 2013 |
21 | Metrobus Transit System for Lahore Ferozepur Corridor Construction of Additional Bridge along Lahore Bridge Package-7 | 800 | NLC | LDA Government of Punjab | NESPAK | May 25, 2012 | February 10, 2013 |
22 | Metrobus Command and Control Center Arfa Karim Tower Lahore | 60 | LDA, TEPA | LDA Government of Punjab | NESPAK | January 17 , 2012 | February 10, 2013 |
23 | Construction of Vehicular Underpass at Model Town Morr Lahore | 600 | LDA/TEPA | LDA Government of Punjab | NESPAK | November 15, 2012 | February 11, 2013 |
24 | Kalma Underpass Lahore | 2065 | LDA/TEPA | LDA Government of Punjab | NESPAK | December 11, 2012 | February 22, 2013 |
25 | Improvement and Rehabilitation of MM Alam Road From Hussain Chowk | 305 | LDA/TEPA | LDA Government of Punjab | ECSP | November 23 ,2012 | March 13, 2013 |
26 | Construction of Flyover and Underpass at Pir Wadhai Morr Rawalpindi. | 890 | NLC | C&W Government of Punjab | Engineering Associates (Pvt) Ltd | October 23, 2012 | March 16, 2013 |
27 | Construction of Underpass Connecting Sector-A Sector-B Askari-11 Lahore | 196 | GHQ | GHQ | Pakistan Consulting Associates J-V (PCA-CEC) | October 16, 2012 | May 31, 2013 |
28 | Construction of Flyover on GT Road in Gujranwala | 3050 | NLC | C&W Government of Punjab | NESPAK | October 23, 2012 | May 31, 2013 |
29 | Construction of Access Road to Quaid-E-Azam Solar Park Bahawalpur | 350 | C&W | C&W Government of Punjab | ECSP | November 12 , 2013 | February 11, 2014 |
30 | New Benazir Bhutto International Airport Islamabad Package 1 Airside Infrastructure (Civil works) (A Joint Venture Of Lagan Construction, Technical Associates and Habib Construction Services) | 10924 | CAA | Aviation Division Government of Pakistan | Mott MacDonald | February 15 , 2010 | May 14, 2014 |
31 | Azadi Interchange Lahore | 3200 | LDA\TEPA | LDA Government of Punjab | NESPAK | January 15, 2014 | June 30, 2014 (Completed in 165 days) |
32 | Construction of Bridge at River Ravi Near Qutab Shahana Sahiwal | 300 | NLC | C&W Government of Punjab | ECSP | November 28, 2013 | August 31, 2014 |
33 | Construction of Bridge over Chenab at Bhowana | 1500 | NLC | C&W Government of Punjab | ACE(Pvt)Ltd | April 01, 2014 | Substantially Completed on January 15, 2015 |
34 | Construction of 17 Storey Bharia Grand Hotel Bharia Town Lahore | 400 | Bharia Town | Bharia Town | Amin Tariq Associates | January 01, 2014 | Substantially Completed on January 15, 2015 |
35 | Metro Bus Project Islamabad Part (Package -1) Faizabad To Peshawar Morr | 3350 | Rawalpindi Development Authority | RDA Government of Punjab | NESPAK | April 23,2014 | March 27, 2015 |
36 | Metro Bus Project Islamabad Construction Bus Depot Near Peshawar Morr, Islamabad | 1125 | Rawalpindi Development Authority | RDA Government of Punjab | NESPAK | November 06,2014 | June 04, 2015 |
37 | Widening and Improvement of Tibba SultanPur to Luddan 32.25 Km | 525 | C&W Provincial Highway Division Multan | C&W Government of Punjab | Engineering General Consultants (Pvt) Limited | June 11 , 2014 | June 10, 2015 |
38 | Khadim-e-Punjab Roads Programme (KPRP) District Lahore. Length=82.590KM | 676 | C&W Provincial Highway Division Lahore | C&W Government of Punjab | A.Z Associates (PVT) LTD | May 15, 2015 | September 30, 2015 |
39 | Khadim-e-Punjab Roads Programme (KPRP) District Gujranwala Length=73.800KM | 617 | C&W Provincial Highway Division Lahore | C&W Government of Punjab | NESPAK | May 15, 2015 | October 31, 2015 |
40 | Construction of Signal Free Corridor Jail Road And Main Boulevard Gulberg Lahore | 1866 | Lahore Development Authority | LDA Government of Punjab | Engineering Associates | July 20, 2015 | February 14 , 2016 |
41 | 2x2.5 Megawatt Hydel Power Projects(FHHP 3/4) At Chashma, Mianwali | 548 | Pakistan Atomic Energy Commission Foundation | Pakistan Atomic Energy Commission Foundation | Pakistan Atomic Energy Commission Foundation | February 2, 2015 | November 1, 2016 |
42 | Development of Greater Iqbal Park Lahore | 1200 | Parks and Horticulture Authority | PHA Government of Punjab | Associated Consulting Engineers(ACE) | October 10, 2015 | November 9, 2016 |
43 | Construction of Metro Bus System Multan Package-5 Vehari Road to Khumaharan Chowk | 4400 | Multan Development Authority | MDA Government of Punjab | Osmani & Company | May 9, 2015 | January 24,2017 |
44 | Construction of Access Road LDA City from Ferozepur Road to Kahna Kacha Road Lahore | 1089 | Lahore Development Authority | Lahore Development Authority | Nespak | February 2, 2016 | April 30, 2017 |
45 | Construction of Road From Thalian on M-2 to New Islamabad International Airport Including periphery Road | 1700 | National Highway Authority | NHA Ministry of Communications Government of Pakistan | M/s Asif Ali Associates Lahore | April 24, 2016 | August 14, 2017 |
46 | Construction of Chaubucha Underpass renamed Beijing Underpass along Canal Road Lahore. (Package-3) Royal Palm Club to Shalimar Interchange Including Asphalt Overlay on Canal Bank Road from Tech Society to Mall Road UnderPass | 3500 | Lahore Development Authority | LDA Government of Punjab | NESPAK | March 31, 2017 Railway Bridge's (July 2017) | November 25, 2017 |
47 | 6 Lane Approach Road to PKLI | 140 | Lahore Development Authority | LDA Government of Punjab | NESPAK | December 5, 2017 | December 25, 2017 |
48 | Dualization of Khanewal Lodhran Road Package - 2&3 Total Length 29.00 KM | 4621 HCS-60% SNMC-40%) | Communication & Works Department | Government of Punjab | NESPAK | May 5, 2017 | May 14, 2018 |