HCS - MM Alam Road - NLC - NHA - Nespak - MBS Lahore - Quaid e Azam Solar Park

 

PROJECTS COMPLETED

 

Project Name
Project Cost (Million Rupees)
Client
Ownership
Consultants
Commencement Date
Completion
Date
Lahore Ring Road Project, Construction of Interchange at Saggian(Package-4).
959
NLC

PMU, Government of Punjab

NESPAK February 3, 2009 May 01, 2009
Lahore Ring Road Project, Construction of Road Portion From Mahmood Booti to Laku Dair(Package-13).
450
NLC
PMU, Government of Punjab NESPAK May 30, 2009
Oct 30, 2009
Lahore Ring Road Project, Construction of Interchange at G.T Road (Package-10).
1500
NLC
PMU, Government of Punjab NESPAK Feb 25, 2009 December 31, 2009 (Early Completion)
Lahore Ring Road Project, Construction of Interchange at Harbanspura Canal Crossing (Package-10).
1200
NLC
PMU, Government of Punjab NESPAK March 01, 2009  January 30, 2010 (Early Completion)
Lahore Ring Road(Package-7) Construction of Abdullah Gull Interchange at Airport Access Road.
1015
NLC
PMU, Government of Punjab NESPAK Sep 12, 2009
 June 11, 2010
(Early Completion)
Dualization of Lahore-kasur Road Group-3 km 49.82 to Km 55.00 Length 518 Km              (Kasur City Portion). 
755
C&W
C&W, Government of Punjab NESPAK April 02, 2010
Oct 01, 2010

(Substantially completed in record period of 2-1/2 Months on June 21, 2010)
Dualization of Lahore Ferozepur Road Lahore to kasur Section. (Km 15.15 to Km 26.65) (length 11.50 K.m) from Kharia Distributory to khana (Phase-1).
220
C&W
C&W, Government of Punjab
NESPAK
June 25, 2010
Sep 24, 2010 Substantially completed on August 30, 2010
Improvement of Road Lahore Branch Canal from Thokar Niaz Baig to Defence Road Including addition of 3rd lane (length 10.96) km in District Lahore.
315
C&W
C&W, Government of Punjab NESPAK December 1, 2010 Substantially Completed on February 28, 2011
Lahore Ring Road (Package 3-B) Construction of Underpass at Jhugian Jodha.
175
NLC
PMU, Government of Punjab
NESPAK
April 15, 2010
February 28, 2011
Lahore Ring Road (Package 11 & 11-A) Construction of Interchange at Ghazi Road upto Bhata Chowk Intersection.               (Sub-Contracted) work from NLC upto WBM level and structures) 
1100
NLC
PMU, Government of Punjab
NESPAK
February 15, 2010
July 30, 2011
Kalma Chowk Fly Over
860
NLC
C&W, Government of Punjab
NESPAK
April 2, 2011
August 14, 2011

(Completed in record time of 135 days)

SOHAWA CHAKWAL TALAGANG MIANWALI ROAD (SECTION BALKASSAR INTERCHANGE TO TERHADA KM 88 TO 154.40) GROUP-1 KM 88 TO KM 115.50 LENGTH = 24.7 KM DISTRICT CHAKWAL BALANCE WORK)
305
C&W 
C&W, Government of Punjab
UMAR MUNSHI
December 11, 2010
September 30, 2011
IMPROVEMENT/REHABILITATION OF MULTAN ROAD FROM THOKAR NIAZ BAIG TO SCHEME MORE (Subcontracted Works from NLC (WBM level, Storm Water Drain and NJ Barrier)
575
NLC
PMU, Government of Punjab
NESPAK
August 06, 2009
October 30, 2011
CONSTRUCTION OF SIALKOT INTERNATIONAL AIRPORT EXTENSION OF APRON
180
SIAL
SIAL
NESPAK
October 02, 2010
November 30, 2011
WIDENING / IMPROVEMENT OF CANAL BANK ROAD, FROM MALL ROAD TO DOCTORS HOSPITAL UNDERPASS (3.5KM)
(Road structure upto base level and footpath)
166
NLC
C&W, Government of Punjab
NESPAK
October 28, 2011
January 15, 2012
WIDENING / IMPROVEMENT OF CONSTRUCTION OF FLYOVER COVERING JUNCTION OF RAWAL ROAD 
CHANDNI CHOWK FLYOVER RAWALPINDI
828
NLC
C&W, Government of Punjab
ENGINEERING ASSOCIATES, KARACHI
 
November 05, 2011

June 30, 2012

(Completed in a record time of 126 days)

CONSTRUCTION OF FLYOVER ALONG FEROZEPUR ROAD JUNCTION
MUSLIM TOWN FLYOVER, LAHORE 
Including at grade works up to WBM level and drainage

 
 

2082

 
 
 
NLC

 

C&W, Government of Punjab

 

NESPAK

 

October 28, 2011

April 21, 2012

(Completed in a record time of 177 days) 
and at grade works on July 31, 2012

WIDENING & IMPROVEMENT OF CHURR CHOWK, G.T ROAD, RAWALPINDI
306
NLC
C&W, Government of Punjab ECSP AUGUST 09, 2012 DECEMBER 1, 2012
CONSTRUCTION OF FLYOVER AT 6th ROAD JUNCTION ALONG MURREE ROAD, RAWALPINDI
814
NLC
C&W, Government of Punjab EA CONSULTING (PVT) LTD SEPTEMBER 25, 2012 January 03, 2013

(Completed in exactly 100 days and made another record)
CONSTRUCTION OF COMPLETE VEHICULAR UNDERPASS AT MODEL TOWN MORR
 
600
TEPA, LDA
LDA, Government of Punjab
NESPAK
AUGUST 28, 2012


 
JANUARY 11, 2013
METRO BUS TRANSIT SYSTEM FOR LAHORE FEROZEPUR CORRIDOR

MAO COLLEGE TO BHATTI CHOWK (LENGTH 2.5 KM) PACKAGE-4
2003
NLC
LDA, Government of Punjab
NESPAK
MAY 29, 2012 FEBRUARY 10, 2013
METRO BUS TRANSIT SYSTEM FOR LAHORE FEROZEPUR CORRIDOR

CONSTRUCTION OF ADDITIONAL BRIDGE ALONG LAHORE BRIDGE PACKAGE-7
800
NLC
LDA, Government of Punjab
NESPAK
MAY 25, 2012 FEBRUARY 10, 2013
BRTS COMMAND AND CONTROL CENTER ARFA KARIM TOWER (5th Floor)

HABIB CONSTRUCTION - IKAN JV
60
TEPA, LDA
LDA, Government of Punjab
NESPAK
JANUARY 17, 2013 FEBRUARY 10, 2013
CONSTRUCTION OF VEHICULAR UNDERPASS AT KALMA CHOWK LAHORE 
 
2065
TEPA, LDA
LDA, Government of Punjab
NESPAK
DECEMBER 11, 2012
 FEBRUARY 22, 2013 

(Completed in a record time of 74 days)
IMPROVEMENT AND REHABILITATION OF MM ALAM ROAD FROM HUSSAIN CHOWK TO MINI MARKET ROUNDABOUT MAIN BOLULEVARD, GULBERG, LAHORE
305
TEPA, LDA
LDA, Government of Punjab
ECSP
NOVEMBER 23, 2012 MARCH 13, 2013
CONSTRUCTION OF FLYOVER AND UNDERPASS AT PIR WADHAI MORR, RAWALPINDI
890
NLC
C&W, Government of Punjab
ECSP
OCTOBER 23, 2012 MARCH 16, 2013
CONSTRUCTION OF UNDERPASS CONNECTING SECTOR-A AND SECTOR-B ASKARI-11, LAHORE
 
196
GHQ HOUSING DIRECTORATE
GHQ Rawalpindi
PAKISTAN CONSULTING ASSOCIATES JV PCA-CEC
OCTOBER 16, 2012 MAY 31, 2013
CONSTRUCTION OF FLYOVER ON GT ROAD IN GUJRANWALA 3050 NLC C&W, Government of Punjab NESPAK,ESCP OCTOBER 23,2012 MAY 31,2013

NEW BENAZIR BHUTTO INTERNATIONAL AIRPORT ISLAMABAD PACAKAGE 1 , AIRSIDE INFRASTRUCTURE (CIVIL WORKS)

(A JOINT VENTURE OF LAGAN CONSTRUCTION, TECHNICAL ASSOCIATES AND HABIB CONSTRUCTION SERVICES PVT. LTD)

 

 

10924

 

 

CAA

 

 

Ministry of Defence, Government of Pakistan

 

 

NESPAK

 

 

February 15,2010

 

 

June 30,2013

(Substantially Completed)

CONSTRUCTION OF ACCESS ROAD TO QUAID-E-AZAM  SOLAR PARK(BAHAWALPUR)

 

350

 

C&W, Department

 

Government of Punjab

ECSP

 

November 12,2013

 

February 11,2014

 

Azadi Interchange 3000 Lahore Development Authority            LDA               Government of   Punjab NESPAK January 15,2014 June 30,2014 (Completed in 165 days)
Construction of Bridge at River Ravi near QUTAB Shaana Sahiwal. 300 NLC C&W, Government of Punjab ECSP November 28, 2013 August 31,2014
 
 
 
 

PROJECTS IN PROGRESS

 


Project Name
Project Cost (Million Rupees)
Client
Ownership
Consultants
Commencement Date
Completion Date
Status
Completed as on October 31,2014
Construction of 16 Storey Bharia Grand Hotel New Block Multan Road Lahore. 400 Bharia Town Bharia Town Amin Tariq Associates January 1, 2014 December 31,2014 81%
Construction of Bridge over Chenab at Bhowana 1500 NLC C&W Government of Punjab NESPAK April 1,2014  December 15,2014 79%
Metro Bus Project Islamabad Part (Package - 1) Faizabad to Peshawar Morr. 3350 Rawalpindi Development Authority RDA Government of Punjab NESPAK April 23,2014 December 23,2014   91%
Construction of 19 Storey Sheraton Golf Resort Hotel,Bahria Golf City Islamabad. 5320 Bahria Town Bahria Town Projacs June 1,2014 January 31,2016   24%
Widening and Improvement of Tibba SultanPur to Luddan 32.25 Km 525         C&W                 Provincial Highway Division        Multan C&W Government of Punjab Engineering General Consultants (Pvt) Limited June 11,2014 June 10,2015   31%

Metro Bus Project Islamabad

Construction Bus Depot near Peshawar Morr, Islamabad

1122

 

Rawalpindi Development Authority

 

RDA Government of Punjab

 

Nespak

 

Declared lowest

 

------

 

------

 

2x2.5 Megawatt Hydel Power Projects(FHHP 3/4) at Chashma, Mianwali

548

Pakistan Atomic Energy Commission Foundation Pakistan Atomic Energy Commission Foundation

------

 

Agreement Signed

------

------

 

 

You are here: Home Projects Projects Completed