HCS - MM Alam Road - NLC - NHA - Nespak - MBS Lahore - Quaid e Azam Solar Park

 

PROJECTS COMPLETED

 

Project Name
Project Cost (Million Rupees)
Client
Ownership
Consultants
Commencement Date
Completion
Date
Lahore Ring Road Project, Construction of Interchange at Saggian(Package-4).
959
NLC

  PMU      Government of Punjab

NESPAK February 3, 2009 May 01, 2009
Lahore Ring Road Project, Construction of Road Portion From Mahmood Booti to Laku Dair(Package-13).
450
NLC
   PMU      Government of Punjab NESPAK May 30, 2009
Oct 30, 2009
Lahore Ring Road Project, Construction of Interchange at G.T Road (Package-10).
1500
NLC
  PMU      Government of Punjab NESPAK Feb 25, 2009 December 31, 2009 (Early Completion)
Lahore Ring Road Project, Construction of Interchange at Harbanspura Canal Crossing (Package-10).
1200
NLC
  PMU      Government of Punjab NESPAK March 01, 2009  January 30, 2010 (Early Completion)
Lahore Ring Road(Package-7) Construction of Abdullah Gull Interchange at Airport Access Road.
1015
NLC
 PMU      Government of Punjab NESPAK Sep 12, 2009
 June 11, 2010
(Early Completion)
Dualization of Lahore-kasur Road Group-3 km 49.82 to Km 55.00 Length 518 Km              (Kasur City Portion). 
755
C&W
 C&W      Government of Punjab NESPAK April 02, 2010
Oct 01, 2010

(Substantially completed in record period of 2-1/2 Months on June 21, 2010)
Dualization of Lahore Ferozepur Road Lahore to kasur Section. (Km 15.15 to Km 26.65) (length 11.50 K.m) from Kharia Distributory to khana (Phase-1).
220
C&W
  C&W     Government of Punjab
NESPAK
June 25, 2010
Sep 24, 2010 Substantially completed on August 30, 2010
Improvement of Road Lahore Branch Canal from Thokar Niaz Baig to Defence Road Including addition of 3rd lane (length 10.96) km in District Lahore.
 
315
 
C&W 

         C&W                Government of           Punjab

                                 NESPAK

December 1, 2010

Substantially Completed on February 28, 2011
Lahore Ring Road (Package 3-B) Construction of Underpass at Jhugian Jodha.
175
NLC
  PMU     Government of Punjab
NESPAK
April 15, 2010
February 28, 2011
Lahore Ring Road (Package 11 & 11-A) Construction of Interchange at Ghazi Road upto Bhata Chowk Intersection.               (Sub-Contracted) work from NLC upto WBM level and structures) 
1100
NLC
PMU
    Government of Punjab
NESPAK
February 15, 2010
July 30, 2011
 
KALMA  FLYOVER
 
860
 
NLC
 
C&W  
 Government of Punjab

NESPAK

 
April 2, 2011
 
August 14, 2011

(Completed in record time of 135 days)

SOHAWA CHAKWAL TALAGANG MIANWALI ROAD (SECTION BALKASSAR INTERCHANGE TO TERHADA KM 88 TO 154.40) GROUP-1 KM 88 TO KM 115.50 LENGTH = 24.7 KM DISTRICT CHAKWAL BALANCE WORK)
 
305
 
C&W 
 
C&W
 Government of Punjab

UMAR MUNSHI

 
December 11, 2010

September30, 2011

IMPROVEMENT/REHABILITATION OF MULTAN ROAD FROM THOKAR NIAZ BAIG TO SCHEME MORE (Subcontracted Works from NLC (WBM level, Storm Water Drain and NJ Barrier)
575
NLC
   PMU     Government of Punjab
NESPAK
August 06, 2009
October 30, 2011
CONSTRUCTION OF SIALKOT INTERNATIONAL AIRPORT EXTENSION OF APRON
180
SIAL
SIAL
NESPAK
October 02, 2010
November 30, 2011
WIDENING / IMPROVEMENT OF CANAL BANK ROAD, FROM MALL ROAD TO DOCTORS HOSPITAL UNDERPASS (3.5KM)
(Road structure upto base level and footpath)
 
166
 
NLC
C&W
   Government of Punjab

NESPAK

 
October 28, 2011

 January 15, 2012

WIDENING / IMPROVEMENT OF CONSTRUCTION OF FLYOVER COVERING JUNCTION OF RAWAL ROAD 
CHANDNI CHOWK FLYOVER RAWALPINDI

828

 
NLC
 
  C&W     Government of Punjab

ENGINEERING ASSOCIATES, KARACHI

 
November 05, 2011

June 30, 2012

(Completed in a record time of 126 days)

CONSTRUCTION OF FLYOVER ALONG FEROZEPUR ROAD JUNCTION
MUSLIM TOWN FLYOVER, LAHORE 
Including at grade works up to WBM level and drainage

 
 
2082
 
 
NLC

                         C&W    Government of Punjab

                  NESPAK

                   October 28, 2011

April 21, 2012

(Completed in a record time of 177 days) 
and at grade works on July 31, 2012

WIDENING & IMPROVEMENT OF CHURR CHOWK, G.T ROAD, RAWALPINDI

 
306
                 NLC

  C&W    Government of Punjab

         ECSP

 AUGUST 09, 2012

DECEMBER 1, 2012

CONSTRUCTION OF FLYOVER AT 6th ROAD JUNCTION ALONG MURREE ROAD, RAWALPINDI

           814
                NLC
                             C&W    Government of Punjab                          EA CONSULTING (PVT) LTD                 September 25,2012                     January 03, 2013

(Completed in exactly 100 days and made another record)
CONSTRUCTION OF COMPLETE VEHICULAR UNDERPASS AT MODEL TOWN MORR
 
600
TEPA, LDA
  LDA     Government of Punjab
NESPAK
AUGUST 28, 2012


 
JANUARY 11, 2013
METRO BUS TRANSIT SYSTEM FOR LAHORE FEROZEPUR CORRIDOR

MAO COLLEGE TO BHATTI CHOWK (LENGTH 2.5 KM) PACKAGE-4
2003
NLC
  LDA     Government of Punjab
NESPAK
MAY 29, 2012 FEBRUARY 10, 2013
METRO BUS TRANSIT SYSTEM FOR LAHORE FEROZEPUR CORRIDOR

CONSTRUCTION OF ADDITIONAL BRIDGE ALONG LAHORE BRIDGE PACKAGE-7
800
NLC
 LDA     Government of Punjab
NESPAK
MAY 25, 2012 FEBRUARY 10, 2013
BRTS COMMAND AND CONTROL CENTER ARFA KARIM TOWER (5th Floor)

HABIB CONSTRUCTION - IKAN JV
60
TEPA, LDA
   LDA     Government of Punjab
NESPAK
JANUARY 17, 2013 FEBRUARY 10, 2013
CONSTRUCTION OF VEHICULAR UNDERPASS AT KALMA CHOWK LAHORE 
 
2065
TEPA, LDA
    LDA     Government of Punjab
NESPAK
DECEMBER 11, 2012
 FEBRUARY 22, 2013 

(Completed in a record time of 74 days)
IMPROVEMENT AND REHABILITATION OF MM ALAM ROAD FROM HUSSAIN CHOWK TO MINI MARKET ROUNDABOUT MAIN BOLULEVARD, GULBERG, LAHORE
305
TEPA, LDA
    LDA     Government of Punjab
ECSP
NOVEMBER 23, 2012 MARCH 13, 2013
CONSTRUCTION OF FLYOVER AND UNDERPASS AT PIR WADHAI MORR, RAWALPINDI
890
NLC
   C&W    Government of Punjab
ECSP
OCTOBER 23, 2012 MARCH 16, 2013
CONSTRUCTION OF UNDERPASS CONNECTING SECTOR-A AND SECTOR-B ASKARI-11, LAHORE
 
196
GHQ HOUSING DIRECTORATE
GHQ Rawalpindi
PAKISTAN CONSULTING ASSOCIATES JV PCA-CEC
OCTOBER 16, 2012 MAY 31, 2013
CONSTRUCTION OF FLYOVER ON GT ROAD IN GUJRANWALA 3050 NLC    C&W    Government of Punjab NESPAK,ESCP OCTOBER 23,2012 MAY 31,2013

NEW BENAZIR BHUTTO INTERNATIONAL AIRPORT ISLAMABAD PACAKAGE 1 , AIRSIDE INFRASTRUCTURE (CIVIL WORKS)

(A JOINT VENTURE OF LAGAN CONSTRUCTION, TECHNICAL ASSOCIATES AND HABIB CONSTRUCTION SERVICES PVT. LTD)

 

 

10924

 

 

CAA

 

 

Ministry of Defence, Government of Pakistan

 

 

NESPAK

 

 

February 15,2010

 

 

June 30,2013

(Substantially Completed)

CONSTRUCTION OF ACCESS ROAD TO QUAID-E-AZAM  SOLAR PARK(BAHAWALPUR)

 

350

 

C&W, Department

 

Government of Punjab

ECSP

 

November 12,2013

 

February 11,2014

 

Azadi Interchange                           

Video Gallery        Image Gallery          

 3000

Lahore Development Authority

            LDA              Government of      Punjab

NESPAK

January 15,2014

June 30,2014 (Completed in 165 days)

(Time Lapse Video)

Construction of Bridge at River Ravi near QUTAB Shaana Sahiwal. 300 NLC C&W    Government of Punjab ECSP November 28, 2013 August 31,2014
 
 
 
 

PROJECTS IN PROGRESS

 


Project Name
Project Cost (Million Rupees)
Client
Ownership
Consultants
Commencement Date
Completion Date
Status
Completed as on December  15,2014
Construction of 17 Storey Bharia Grand Hotel Bharia Town Lahore. 400 Bharia Town Bharia Town Amin Tariq Associates January 1, 2014 December 31,2014 90%
Construction of Bridge over Chenab at Bhowana. 1500 NLC C&W Government of Punjab NESPAK April 1,2014  February 28,2015  81%
Metro Bus Project Islamabad Part (Package - 1) Faizabad to Peshawar Morr. 3350 Rawalpindi Development Authority RDA Government of Punjab NESPAK April 23,2014 January 30,2015  90%
Construction of 19 Storey Sheraton Golf Resort Hotel,Bahria Golf City Islamabad. 5320 Bahria Town Bahria Town Projacs June 1,2014 January 31,2016   25%
Widening and Improvement of Tibba SultanPur to Luddan 32.25 Km. 525         C&W                 Provincial Highway Division        Multan C&W Government of Punjab Engineering General Consultants (Pvt) Limited June 11,2014 June 10,2015   37%

Metro Bus Project Islamabad

Construction Bus Depot near Peshawar Morr, Islamabad.

1125

 

Rawalpindi Development Authority

 

RDA Government of Punjab

 

Nespak

 

     November     6,2014

 

March 6,2015

 

  50%

2x2.5 Megawatt Hydel Power Projects(FHPP 3/4) at Chashma, Mianwali.                  

(Dynamic Demo Model Video)

548

Pakistan Atomic Energy Commission Foundation Pakistan Atomic Energy Commission 

WASO

 

November 28,2014

May 28,2016

   0%

 

 

You are here: Home Projects Projects Completed