KALMA UNDERPASS LAHORE

OVERVIEW

The Kalma Chowk intersection was one of the busiest in Lahore, Pakistan, with traffic volume often reaching as many as 393,000 vehicles per day. Two major roads—Ferozepur Road and the joining of Main Boulevard Garden Town (Barket Market Road) and Main Boulevard Gulberg Liberty Market Road)—meet at this junction. Long lines were common during peak traffic times, and a vehicle had to wait for up to eight minutes. Construction of underpass on such a busiest location just in 74 days truly exhibits the capabilities of HCS.

PROJECT STATISTICS

</p> <p> [align-left][align-left]
Project Location:Lahore
Client:LDA, TEPA
Ownership: LDA, Government of Punjab
Consultant:Nespak
Project Value:PKR. 2,065 Million
HCS Share60%
Start Date:December 11, 2012
Completion Date:February 22, 2013
Completed in a Record Time of 74 Days
</p> <p>

PROJECT HIGHLIGHTS

</p> <p>[align-left][align-left]
Excavation:177,297 m3
Base/Sub Base:26,284 m3
Concrete34,439 m3
Asphalt15,989 m3
Reinforcement4,063 Ton