KALMA CHOWK FLYOVER PROJECT

 

Habib Construction Services (Pvt.) Ltd. has great work done at Kalma Chowk Flyover Project, and made a new world record after beat to Kelaniya flyover project (phase-I) in Sri Lanka.

The Kelaniya flyover on the Colombo-Kandy road. The length of the Kelaniya flyover is 325 meters. Under the first phase of the Kelaniya flyover, two lanes have been constructed in just 60 days setting a world record. Phase-II of the Kelaniya flyover also constructed on two (2) lanes after long time completion of Phase-I.

Details available at: http://www.rda.gov.lk/supported/flyovers/kelaniya/kelaniya.htm

While Habib Construction Services (Pvt.) Ltd. constructed Kalma Chowk Flyover Project, based on two(2) bridges of three (3) lanes, 500 meters long in just 135 days, that’s a new world record in the history of flyovers construction.

 

Posted in Uncategorized | Leave a comment

135 Day’s a Record Duration Complete of Kalma Chowk Flyover

Posted in Uncategorized | 1 Comment

Kalma Chowk: ‘To Lahore, happy Independence Day’

Kalma Chowk:

Posted in Uncategorized | Leave a comment

Kalma Chowk Flyover Under-construction photo

 

An arial view of Kalma Chowk under-construction flyovers

 

Posted in Ongoing Projects | Leave a comment

Kalma Chowk Opening News

Kalma Chowk Flyover Opening News as on daily jang newspaper, dated 15th of August, 2011

Posted in Uncategorized | Tagged | Leave a comment

Kalma Chowk Flyover

Kalama Chowk Flyover Lahore if completed in 135 days would be a world record. The length of Kalama flyover is 500 meters. Three plus three lane two separate bridges, located in Heart of the Lahore City would be completed in just 135 days on August 14, 2011.
Previously Kelaniya flyover project in Sri Lanka a 325 meters long two lane bridge was completed in just 60 days setting a world record.

The record was earlier held by the Philippines. The Philippines Government completed assembling a prefabricated 300 meters long Malos flyover in Manila in 66 days.
Kalma Flyover Lahore is almost three times bigger than both above referred flyovers

http://www.slcricket.com/mother-lanka/15002-kelaniya-flyover-completed-world-record-time.html

Posted in Uncategorized | Tagged | 11 Comments

Lahore Kalma Chowk Project

HCS team is working on the said project and it is assumed that the project shall be completed at the given period of time.

Posted in Ongoing Projects | 2 Comments